The U.S. Energy Information Administration reports that North Americaโ€™s LNG export capacity is on track to more than double by 2028. They write:

North Americaโ€™s liquefied natural gas (LNG) export capacity is on track to more than double between 2024 and 2028, from 11.4 billion cubic feet per day (Bcf/d) in 2023 to 24.4 Bcf/d in 2028, if projects currently under construction begin operations as planned. During this time, we expect developers in Mexico and Canada to place their first LNG export terminals into service and in the United States to add to existing LNG capacity. By the end of 2028, we estimate LNG export capacity will grow by 0.8 Bcf/d in Mexico, 2.5 Bcf/d in Canada, and 9.7 Bcf/d in the United States from a total of 10 new projects that are currently under construction in the three countries.

Mexico.ย Developers are currently constructing two projects with a combined LNG export capacity of 0.6 Bcf/dโ€”Fast LNG Altamiraย offshore on Mexico’s east coast and Energรญa Costa Azul on Mexico’s west coast.

  • Fast LNG Altamira consists of two Floating LNG production units (FLNG), each with a capacity to liquefy up toย 0.199 Bcf/dย of natural gas, located off the coast of Altamira, in the state of Tamaulipas, Mexico. Natural gas from the United States delivered via theย Sur de Texas-Tuxpan pipelineย will supply these units. Theย first LNG cargoย from this facility was shipped in August 2024.
  • Theย Energรญa Costa Azul LNG export terminalย (0.4 Bcf/d export capacity) is located at the site of the existing LNG regasification (import) terminal in Baja California in western Mexico. Developers proposed an expansion of this project in Phase 2 by 1.6 Bcf/d. This project will be supplied with natural gas from the Permian Basin in the United States.

Developers have proposed other LNG export projects, all for Mexicoโ€™s west coast, includingย Saguaro Energia LNGย (2.0 Bcf/d capacity),ย Amigo LNGย (1.0 Bcf/d capacity),ย Gato Negro LNGย (0.6 Bcf/d capacity),ย Salina Cruz LNGย (0.4 Bcf/d capacity), andย Vista Pacifico LNGย (0.5 Bcf/d capacity), with a combined capacity of 4.5 Bcf/d; however, none of these projects have reached a final investment decision or started construction.

Canada.ย Currently, three LNG export projects with a combined capacity of 2.5 Bcf/d are under construction in British Columbia on Canadaโ€™s west coast. Developers ofย LNG Canadaย (1.8 Bcf/d export capacity) plan to start LNG exports from Train 1 in the summer of 2025.ย Woodfibre LNGย (export capacity 0.3 Bcf/d) targets the startup of LNG exports in 2027.ย Cedar LNGโ€”an FLNG project with capacity to liquefy up to 0.4 Bcf/dโ€”made a final investment decisionย in June 2024 and expects to start LNG exports in 2028. These projects will be supplied with natural gas from western Canada.

In addition, theย Canada Energy Regulator (CER) has authorizedย four LNG export projects, including an expansion of LNG Canada, with a combined proposed LNG export capacity of 4.1 Bcf/d.

United States.ย Five LNG export projects are currently under constructionย with a combined export capacity of 9.7 Bcf/dโ€”Plaquemines (Phase I and Phase II), Corpus Christi Stage III, Golden Pass, Rio Grande (Phase I), and Port Arthur (Phase I). Developers expect to produce the first LNG from Plaquemines LNG and Corpus Christi LNG Stage III and ship first cargoes from these projects by the end of 2024.

Read more here.